Bring the door-set information and partition design together before ordering frames or closing the wall around an opening.

A door set and the wall around it have to be coordinated as one opening. The frame needs an appropriate supporting construction, and its dimensions must work with the finished partition. Where fire resistance or sound insulation is required, the selected door arrangement also has to suit that purpose. A joinery schedule and a partition specification prepared separately can leave gaps between the two packages. Resolve those gaps before materials are ordered.
Start with the actual door set
Obtain the proposed door-set information rather than working from a leaf width alone. The frame, leaf, seals, fittings and installation requirements define what must fit within the opening. Ask the supplier to identify the wall constructions covered by the relevant evidence and the details it needs from the partition designer.
The door's use matters too. A frequently used office entrance, an access-controlled store and a meeting-room door impose different coordination questions. Record the chosen closer, access-control equipment and any other fittings early enough for their support and service needs to be considered. These items should appear on the opening information issued to both trades.
British Gypsum's partition details distinguish different door-support arrangements and direct the reader to consult the door manufacturer. Their drawings have defined limits. They are a reference for the selected system, not permission to choose a convenient sketch and apply it to any door. The project detail must account for the actual door set and wall.
Resolve three different dimensions
The opening in the framing, the outside of the frame and the usable passage through the finished door are different dimensions. Put each on the appropriate drawing and identify its reference faces. This avoids the common ambiguity of a note that says door width without explaining what has been measured.
Include the finished partition thickness, taking account of its board layers and specified finish. A frame ordered for a thinner construction may cause difficulty even if the plan position is correct. At an adjoining return, check the relationship between the frame, architrave or trim and the completed wall face. Skirting and other joinery can also affect the visible result.
Where accessibility or escape requirements affect the opening, the responsible designer should confirm the relevant dimensions and hardware arrangement. The coordination record should then carry that confirmed information into procurement.
Scroll sideways to see the full table. Keyboard: focus the table, then use the arrow keys.
| Item | Information required | Who supplies or confirms it |
|---|---|---|
| Door set | Frame and leaf references; fittings; installation evidence | Door-set supplier and project designer |
| Framed opening | Set-out dimensions and supported opening detail | Partition designer coordinated with supplier |
| Finished wall | Thickness, layers, finish and junctions | Drylining specification |
| Usable passage | Required opening and any operational constraints | Responsible designer |
| Inspection | Evidence needed before concealment and at completion | Project team and relevant installers |
Agree support and fixing before the opening is built
The partition designer needs the information that affects jamb and head support. That includes the actual door arrangement and the way its frame is attached. A door opening interrupts the ordinary wall framing, so the general stud layout cannot answer every question at that point.
Obtain the selected detail with its component references and installation requirements. If the proposed opening falls outside a published detail's scope, raise that with the relevant technical team before construction. An extra piece of timber or steel selected on site may change the arrangement without providing the evidence required for the door and wall.
Allocate supply and installation of concealed support explicitly. It might sit within the drylining package, but the joinery supplier still needs to know what will be there. The two teams should agree when the opening will be available for checking and which parts must remain visible. Photographs can help identify what was installed, provided they are tied to the opening reference and do not replace required inspections.

Treat fire and acoustic requirements separately
A fire-resisting wall and a fire door need compatible, documented interfaces. The door's supporting construction, installation and perimeter treatment require consideration alongside the wall. The responsible designer determines the required fire strategy; a board description or a door label alone does not establish that the finished opening satisfies it.
For sound insulation, the door is part of the room boundary. British Gypsum advises consultation with door manufacturers and acoustic specialists where acoustic requirements apply. The acoustic brief should address the opening, its seals and the rest of the boundary rather than selecting a partition from a laboratory rating and ignoring the doorway.
Keep the fire and acoustic decisions in distinct fields in the opening record. They may influence the same hardware or junction, but they answer different questions and rely on different evidence. Where one proposed change affects both, obtain a coordinated response instead of accepting two disconnected approvals that describe different constructions.
Coordinate finishing and the installation order
Ask the door supplier which surfaces and dimensions it needs before the frame is installed, and which finishing operations follow. Different door-set systems can have different sequences. The accepted programme should show the chosen arrangement rather than assume that all joinery is fitted at the same stage.
Consider access for fixing and checking both sides of the frame. If a wall face is closed or a trim fitted too early, the relevant connection may be hidden before the person responsible has checked it. Conversely, leaving a vulnerable finished door in a busy delivery route can create avoidable damage. Agree protection and responsibility for making good within the actual site programme.
Record the boundary between the drylining finish and the frame installation. Identify who completes the reveal, perimeter treatment, decoration and final adjustment. A phrase such as door by others leaves these tasks unresolved. The opening record can be short, but it should name a responsible package for every interface that will otherwise be concealed or left unfinished.
- Issue the selected door-set information with the wall type.
- Agree the opening support and installation detail.
- Check the frame opening at the stated inspection stage.
- Complete the coordinated fixing, perimeter and finishing work.
- Carry out the required final checks and retain the opening record.
Deal with late changes through the opening reference
Suppose, hypothetically, that a client changes a meeting-room door after the partition frame is installed. The first question is which opening is affected and what has changed: the frame dimensions, leaf arrangement, weight, fittings or performance evidence. A product name by itself is insufficient to assess the impact.
The project team should then check the installed support against the revised door information and determine any alteration required. That review may affect concealed work, finished thickness or neighbouring services. Record the authorised response before the original opening is covered, and distinguish the revised work from making good that was already included.
For a Cheshire refurbishment enquiry, send the door schedule with the marked-up floor plan and wall-type references. Include any existing doors to be retained, because their relationship to new linings also needs checking. A quotation based on this coordinated package can describe the actual opening work and identify unresolved supplier information without pretending every doorway is identical.
Questions and answers
Can an existing door be retained in a new partition?
Possibly, but its construction, condition, dimensions and required function must be assessed. Retention should be an explicit design decision with a suitable surrounding detail. An existing door should not acquire a new fire or acoustic claim simply because it is moved into a new wall.
Who is responsible for the final adjustment?
Agree that in the package scope before ordering. The door installer, drylining contractor and project coordinator need a clear division of fixing, finishing and adjustment work. The completed door then needs the checks appropriate to its specified function.
Sources and further reading
- British Gypsum White Book: partitions and GypWall Single FrameRelease/version: Introduction updated 8 January 2026; GypWall Single Frame section updated 1 December 2025Source checked: 21 November 2026
- British Gypsum — White Book: System Design PrinciplesRelease/version: Relevant principles sections: 11 September 2023Source checked: 21 November 2026
- GOV.UK — Approved Document B publication and amendmentsRelease/version: Publication page updated 16 September 2026Source checked: 21 November 2026